My only press setter is out for three days. What are my options, and what do they cost?
When the only person who can do the job is out: pricing the ways through.
Hemanth Nunna, Co-founder and CEO, Corrid · November 23, 2026 · 5 min read
Dana is the only setter for Press 2, and she is out Wednesday to Friday. Press 2 needs a die change on Thursday for order 4471: 12,000 brackets for Northfield Trailers. Nobody else has set that die.
This is the problem no ledger shows. The press is on the balance sheet; the fact that only Dana can set it is not. It is still worth money, and the clearest way to see how much is to price the three days.
The ways through
- Marco, who sets Press 1, sets it Thursday evening
- Working4 h overtime × $52 × 1.5 = $312; an extra first-piece check, 1 h × $40
- Cost$352
- An outside setter from a tooling shop
- Working6 h × $95 = $570, plus a $150 call-out
- Cost$720
- Wait for Dana on Monday
- WorkingPress 2 idle Thursday and Friday, 16 h × $185 = $2,960; ships 2 days late, and this order’s late clause has no grace days: 2 × $1,245.60
- Cost$5,451.20
| Way through | Working | Cost |
|---|---|---|
| Marco, who sets Press 1, sets it Thursday evening | 4 h overtime × $52 × 1.5 = $312; an extra first-piece check, 1 h × $40 | $352 |
| An outside setter from a tooling shop | 6 h × $95 = $570, plus a $150 call-out | $720 |
| Wait for Dana on Monday | Press 2 idle Thursday and Friday, 16 h × $185 = $2,960; ships 2 days late, and this order’s late clause has no grace days: 2 × $1,245.60 | $5,451.20 |
On cost alone, Marco wins. But the cheapest row carries a risk the others do not: he has never set this die. That is why the extra first-piece check is in the price. If the first parts are wrong, the cost is scrap and a second set-up, and the outside setter starts to look cheap.
The real question: what does the gap cost a year?
One absence is a bad week. The pattern is the cost. If Dana is out twice a year at a bad moment and the fix is usually the expensive row, a single person is costing you about $10,900 a year.
Training a second setter
40 hours of Dana’s time and a trainee’s time: 40 × ($48 + $34) = $3,280
Against $5,451.20 for one bad week, training a second person pays for itself the first time it is needed. It also changes what you can promise: a date that rests on two people is a safer date than one that rests on one.
- List the jobs only one person can do. Most manufacturers find three or four.
- For each, write down what three days without that person would cost, using the table above.
- Start with the most expensive one. Training is a cost you choose; an absence is not.
This is the work Corrid does when a key person is out: it finds who else can do the work, prices each way through, and keeps the orders moving. The figures here are illustrative; use your own rates.
About the author
Hemanth Nunna
Hemanth leads Corrid. He has spent a decade inside the businesses that make things, from the plant floor to the boardroom.