Notes

My supplier just raised prices. What does it cost me, and can I pass it on?

A supplier raised prices mid-contract. What it costs you, and how to ask your customers to share it.

Hemanth Nunna, Co-founder and CEO, Corrid · November 19, 2026 · 6 min read

The letter says coil goes up $0.14 a kilogram from 1 December. Most shops read it, sigh, and find out what it really cost them at month-end, when the margin on three or four orders comes in lower than quoted. By then it is too late to ask anyone to share it.

The same answer is available on the day the letter arrives. It takes four questions, and none of them needs more than a calculator.

1. Which open orders does it touch?

Not every order. Only the ones that will be made from material you have not bought yet. Coil already on your floor was bought at the old price, so the rise only reaches orders that ship after that stock runs out.

Go through your open orders and mark each one that uses this material and ships after 1 December. For each, note how many parts and how much material each part uses, including scrap: if a bracket weighs 0.57 kg and the strip loses about 8 percent to the skeleton, budget 0.62 kg a part.

2. What does it cost on each one?

Added cost of an order

parts × kg per part (with scrap) × increase per kg

Northfield Trailers, brackets
Parts12,000
kg a part0.62
Coil (kg)7,440
Added cost$1,041.60
Wellington Trailers, bracket BR-204
Parts8,000
kg a part0.48
Coil (kg)3,840
Added cost$537.60
Grand River Ag, hitch plates
Parts3,500
kg a part1.90
Coil (kg)6,650
Added cost$931.00
Total
Coil (kg)17,930
Added cost$2,510.20
An illustrative stamping shop, three open orders on coil, increase of $0.14/kg

Now take off what your stock covers. If 3,000 kg is on the floor at the old price, it covers the start of the Northfield order, and the real exposure drops by 3,000 × $0.14 = $420, to $2,090.20.

Then put each number next to the margin you quoted. On the Northfield order, $1,041.60 is about 4 percent of a $24,900 margin. On a thin job the same rise can take most of it. That comparison, not the total, tells you where to spend your effort.

3. Who can you ask?

Read the terms of each order before you pick up the phone. Some have a material surcharge or price adjustment clause tied to an index; there you are entitled to pass it on and only need to show the working. Some are fixed price; there you can still ask, but it is a request, and the relationship decides the answer.

  • Clause in the contract: pass it on in full, with the calculation attached.
  • Fixed price, long relationship, large exposure: ask to share it, for example half each, and say why.
  • Fixed price, small exposure: often cheaper to absorb it and say so. That is a decision too; write it down so it is not forgotten at the next quote.

4. Ask early, and show the working

A customer told on the day, with the numbers, has time to plan. A customer told on the invoice feels ambushed. The note does not need to be long.

An example note to a customer

Hi Sam, our coil supplier has raised the price by $0.14/kg from 1 December. Your order of 8,000 BR-204 brackets uses 3,840 kg, so it adds $537.60, or about $0.07 a bracket. Our terms allow a material adjustment; we would like to apply it to this order only and hold the price on the next one while we look for another source. The calculation is attached. Happy to talk it through.

What to keep

Write down what you asked, what each customer said and what you decided. Next time a price moves, you will know which customers share costs, which clauses work, and what an hour of this work saved you.

This is the work Corrid does in its cost-change case: it finds every part and open order a new price touches, prices each one against the margin you quoted, and drafts the note to each customer for your approval. The numbers in this note are illustrative; use your own.

About the author

Hemanth Nunna

Hemanth leads Corrid. He has spent a decade inside the businesses that make and move things, from the plant floor to the boardroom.